The current developments of the project are as follows:
1. 102 Foundations completed
2. 55 Buildings crossed 1st level of slab
3. 24 Buildings crossed 2nd level of slab
4. 10 Buildings Roof completed
5. 01 Buildings Roof work in progress
6. 30 Cubic mtr/hr capacity RMC plant installed at site
7. New form work system with M.S. shuttering developed
8. Overall Construction Activity in full swing